Community Cohesion and Vibrancy
Frank Weston Rose Garden Redevelopment
Frank Weston Rose Garden Redevelopment
Start Date: 03/15/2024
End Date: 12/31/2026
Priority: High
Level of Effort: High
Level of Impact: High
Percent Complete: 100%
Current Status:
Nunes Connecticut, Inc. installed the stair railing from Silas Deane Highway following approvals of plans by the Building Department. Fresh Start Worx constructed and delivered 8 tuteur plant stands, which will be incorporated into the garden in the spring.
The project is now complete.
A dedication ceremony is planned for June 2026.