Cove Park Heritage Way Trail Improvements
Cove Park Heritage Way Trail Improvements

Start Date: 09/01/2023

End Date: 01/01/2028

Priority: Medium

Level of Effort: Medium

Level of Impact: Medium

Percent Complete: 15%

Current Status:

The Town submitted a Capitol Region Council of Governments (CRCOG) Local Transportation Capital Improvement Program (LOTCIP) grant application in the amount of $1,478,400 to support design and construction improvements to the Heritage Way Trail at Cove Park.

The proposed project includes improvements to approximately 2,900 linear feet of existing trail, as well as reconstruction of the Solomon Welles House driveway and gravel parking lot.

The Town is also awaiting a decision on a Connecticut DEEP Recreational Trails Program grant request of $560,000, with a required $140,000 (20%) local match. Parks and Recreation has submitted the match as a CIP project.

Legend: Completed Previous Qyarter Status Icon Completed Previous Quarter | TCompleted Last Quarter Status Icon Completed Last Quarter | Up Arrow Status Icon On Target | Yellow Square Status Icon On Hold | Down Arrow Status Icon Below Plan |Blue Circle Status Icon No Information
Wethersfield Town Hall​
505 Silas Deane Highway ​
Wethersfield, CT 06109​
Contact 860-721-2800​

www.wethersfieldct.gov​