Spring St Pond Park & Dam Improvements (30043)
Spring St Pond Park & Dam Improvements (30043)

Start Date: 07/21/2020

End Date: 08/30/2028

Priority: High

Level of Effort: Medium

Level of Impact: High

Percent Complete: 10%

Current Status:

Macchi Engineers provided 30% conceptual plans for bike path and preliminary park improvements.  Staff have reviewed the plans and provided comments.

The next step is to schedule a pre-application meeting with the CT DEEP.

An extension of the contract with Macchi Engineers will be required to continue the project.

Legend: Completed Previous Qyarter Status Icon Completed Previous Quarter | TCompleted Last Quarter Status Icon Completed Last Quarter | Up Arrow Status Icon On Target | Yellow Square Status Icon On Hold | Down Arrow Status Icon Below Plan |Blue Circle Status Icon No Information