Public Facilities and Infrastructure
Utility Project Coordination
Utility Project Coordination
Start Date: 01/01/2023
End Date: 12/31/2027
Priority: Low
Level of Effort: Low
Level of Impact: High
Percent Complete: 0%
Current Status:
MDC Silas Deane Highway Watermain Project: Construction is underway.
MDC Coppermill Rd Water Main: Construction is underway with paving in 2026.
MDC Stillwold Rd Water Main: Scheduled to start in 2026 or 2027.
MDC Surrey Dr Water Main: Scheduled to start in 2026.
CNG Prospect & Wolcott Hill Rd Gas Main: Construction is underway.
FiberOptic Upgrade: Construction is underway, which is mostly overhead or off-road. Issues along Hang Dog Ln have been addressed.