Old Academy interior building renovation (30634)
Old Academy interior building renovation (30634)

Start Date: 02/01/2024

End Date: 12/31/2030

Priority: High

Level of Effort: High

Level of Impact: High

Percent Complete: 2%

Current Status:

Initial conceptual designs have been developed. This project has some overlap with the cupola restoration and reattachment project in terms of investigation being needed within the ceiling on the second floor. Scaffolding was erected to investigate within the second floor ceiling to determine the best way to proceed with HVAC and lighting improvements in addition to cupola reinstallation.

Legend: Completed Previous Qyarter Status Icon Completed Previous Quarter | TCompleted Last Quarter Status Icon Completed Last Quarter | Up Arrow Status Icon On Target | Yellow Square Status Icon On Hold | Down Arrow Status Icon Below Plan |Blue Circle Status Icon No Information
Wethersfield Town Hall​
505 Silas Deane Highway ​
Wethersfield, CT 06109​
Contact 860-721-2800​

www.wethersfieldct.gov​