Public Facilities and Infrastructure Icon

Public Facilities and Infrastructure

Cove Park Entrance Improvements (30454)
Cove Park Entrance Improvements (30454)

Start Date: 07/01/2024

End Date: 12/31/2027

Priority: Medium

Level of Effort: High

Level of Impact: Medium

Percent Complete: 95%

Current Status:

Suchocki and Son is awaiting installation of the light due to spring flooding at Cove Park.

The contractor will also return in the spring to reseed the island.

Legend: Completed Previous Qyarter Status Icon Completed Previous Quarter | TCompleted Last Quarter Status Icon Completed Last Quarter | Up Arrow Status Icon On Target | Yellow Square Status Icon On Hold | Down Arrow Status Icon Below Plan |Blue Circle Status Icon No Information
Wethersfield Town Hall​
505 Silas Deane Highway ​
Wethersfield, CT 06109​
Contact 860-721-2800​

www.wethersfieldct.gov​