Public Facilities and Infrastructure
Cove Park Entrance Improvements (30454)
Cove Park Entrance Improvements (30454)
Start Date: 07/01/2024
End Date: 12/31/2027
Priority: Medium
Level of Effort: High
Level of Impact: Medium
Percent Complete: 95%
Current Status:
Suchocki and Son is awaiting installation of the light due to spring flooding at Cove Park.
The contractor will also return in the spring to reseed the island.
Legend:
Completed Previous Quarter |
Completed Last Quarter |
On Target |
On Hold |
Below Plan |
No Information