Public Facilities and Infrastructure
Old Academy cupola restoration/reconstruction (30634)
Old Academy cupola restoration/reconstruction (30634)
Start Date: 05/01/2023
End Date: 11/30/2027
Priority: Medium
Level of Effort: High
Level of Impact: Medium
Percent Complete: 50%
Current Status:
The restoration firm has completed work on the cupola itself. The consultant has also completed the investigation regarding reattachment. During the investigation it was found that stabilization work is required on the truss system located below the room and above the second floor ceiling. A funding application has been submitted for Congressional Directed Spending for this project. Meanwhile, cupola reattachment is on hold, and the completion date of the cupola project is being pushed out to next fall.
Legend:
Completed Previous Quarter |
Completed Last Quarter |
On Target |
On Hold |
Below Plan |
No Information