Public Facilities and Infrastructure Icon

Public Facilities and Infrastructure

Tree Replacement (30635)
Tree Replacement (30635)

Start Date: 10/16/2023

End Date: 12/31/2026

Priority: Medium

Level of Effort: Medium

Level of Impact: Medium

Percent Complete: 72%

Current Status:

The Tree Warden has been moving this project forward. Plantings include; 30 street trees in Fall 2024, 26 in Spring 2025, and an additional 25 in Fall 2025. Additional plantings are scheduled for Spring and Fall 2026. All water bags were purchased in 2024, and the funds allocated for the water trailer setup were used to build it last fall.

Legend: Completed Previous Qyarter Status Icon Completed Previous Quarter | TCompleted Last Quarter Status Icon Completed Last Quarter | Up Arrow Status Icon On Target | Yellow Square Status Icon On Hold | Down Arrow Status Icon Below Plan |Blue Circle Status Icon No Information
Wethersfield Town Hall​
505 Silas Deane Highway ​
Wethersfield, CT 06109​
Contact 860-721-2800​

www.wethersfieldct.gov​